Reorder level, safety stock and reorder quantity: formulas with worked examples
Short answer
Reorder level = average daily use × supplier lead time in days + safety stock. Safety stock covers the days when use is higher or the supplier is late; a simple version is (maximum daily use × maximum lead time) − (average daily use × average lead time). When stock falls to the reorder level, raise a purchase request for the reorder quantity, often set with the EOQ formula √(2 × annual demand × cost per order ÷ holding cost per unit per year). Set levels per warehouse and review them every quarter.
The formulas
| Term | Formula |
|---|---|
| Reorder level | Average daily use × lead time (days) + safety stock |
| Safety stock (simple) | (Max daily use × max lead time) − (average daily use × average lead time) |
| Economic order quantity (EOQ) | √(2 × annual demand × cost per order ÷ holding cost per unit per year) |
| Maximum level | Reorder level + reorder quantity − (minimum daily use × minimum lead time) |
Worked example
A packaging unit uses corrugated boxes:
| Input | Value |
|---|---|
| Average use | 400 boxes a day |
| Maximum use | 550 boxes a day |
| Average lead time | 5 days |
| Maximum lead time | 7 days |
| Annual demand | 1,20,000 boxes |
| Cost per order | ₹1,500 |
| Holding cost | ₹4 per box per year |
- Safety stock = 550 × 7 − 400 × 5 = 3,850 − 2,000 = 1,850 boxes.
- Reorder level = 400 × 5 + 1,850 = 3,850 boxes.
- EOQ = √(2 × 1,20,000 × 1,500 ÷ 4) = √9,00,00,000 = 9,487 boxes, rounded to the supplier's pack size.
Making it work in practice
- Per warehouse: each site has its own use and lead time.
- Count stock on the way: include goods in transit between your warehouses, or you'll order twice.
- Watch the near-misses: items within 20% above their level are next week's shortages.
- Review quarterly and after any change in supplier or demand.
- Daily check: one list each morning of items at or below level beats a monthly surprise.
How flowwork.ai solves this
- Reorder levels per warehouse on each item, with an optional reorder quantity.
- Inventory › Reorder lists items at or below their level (counting stock in transit to that warehouse), and Below or near adds those within 20% above it.
- Create requisition turns the ticked lines into a draft requisition in FlowProcure, in your name, with the reorder quantity (or twice the level less what is there). Lines are matched to the linked Procurement items.
- 09:00 bell note each morning to people who post stock, when items are below their level, and workflow rules can act on the same event.
Safety stock and EOQ aren't calculated for you: work them out with the formulas above and set the level. See the FlowInventory and purchase request approvals.
Frequently asked questions
What is the formula for reorder level?
Reorder level = average daily use × lead time in days + safety stock.
How do I calculate safety stock?
A simple method: (maximum daily use × maximum lead time) − (average daily use × average lead time).
What is EOQ?
Economic order quantity, the order size that balances ordering cost and holding cost: √(2 × annual demand × cost per order ÷ holding cost per unit per year).
Sources
- ICAI Board of Studies: Cost and Management Accounting study material (checked 24 November 2026)
Spotted something out of date? Tell us and we'll correct it.